This week they got some of the siding put up around the windows, the eaves trimmed and the roof ready to shingle.
Due to the slope of the lot and a miss-communication with the company that poured the basement, the brick ledge had to be re-cut so that it was lower.
They hung the garage doors this week, they are insulated and finished on the inside.
Here is a picture of the gas fired heat pump in the basement.
This is a shot of the windows in the basement with the fire escape ladders installed.
No comments:
Post a Comment