Sunday, August 28, 2011

New Home Week 6

This week they got some of the siding put up around the windows, the eaves trimmed and the roof ready to shingle.

Due to the slope of the lot and a miss-communication with the company that poured the basement, the brick ledge had to be re-cut so that it was lower.

They hung the garage doors this week, they are insulated and finished on the inside.

Here is a picture of the gas fired heat pump in the basement.

This is a shot of the windows in the basement with the fire escape ladders installed.